GST/HST on Progress Billings and Holdbacks
The short version
- GST/HST on a progress billing is payable on the earlier of the day the customer pays it and the day it becomes due. It becomes due on the earlier of the invoice date and the due date set in your written contract.
- The holdback has its own rule: GST/HST on the held-back part is payable on the earlier of the day the holdback is paid and the day it becomes payable. In Ontario, 13% on a $5,000 holdback is $650, and it is due in that earlier period even if the owner pays late.
- Under a written construction contract, any part of the price not yet billed or paid is taxable at the end of the month after the month the work is substantially complete, which the CRA treats as 90% or more of the work done. That catch-all rule does not apply to holdbacks.
- A contractor's request for payment that still has to be certified by an architect, engineer or consultant is not an invoice, so it does not trigger the tax by itself.
- Your customer, if registered, claims the input tax credit (ITC) in the period the tax becomes payable, and has four years (for most registrants) to claim it.
GST/HST on Progress Billings and Holdbacks
Construction money arrives in pieces. You bill a draw, the owner or general contractor holds back a slice under Ontario's Construction Act, and the last cheque shows up months after the drywall dust has settled. GST/HST follows each piece on its own clock, and that clock does not always wait for the cheque. Get the clocks right and your returns are on time; get them wrong and you report tax late and pay interest for the privilege.
When GST/HST Is Payable on Each Amount
| Amount | GST/HST becomes payable | Rule |
|---|---|---|
| Progress billing (draw) | Earlier of the day it's paid and the day it becomes due | Excise Tax Act 168(1) and 168(2) |
| Holdback retained under a written construction contract or a provincial Act | Earlier of the day the holdback is paid and the day it becomes payable | 168(7) |
| Unbilled balance after substantial completion | Last day of the month after the month the work was substantially complete (the CRA treats this as 90% or more done) | 168(3)(c) |
| Security deposit | When it's applied to the price | See GST/HST on deposits |
Each progress payment is taxed on its own amount when it is paid or due. You don't charge tax on the whole contract at the first draw, and you don't wait for the final invoice either.
A Worked Ontario Example
You have a $200,000 written contract to build an addition in Barrie, plus 13% HST. In Ontario, the Construction Act requires each payer to retain a holdback equal to 10 per cent of the price of the services or materials as they are actually supplied (section 22(1)). In March you bill a $50,000 draw.
- The owner pays $45,000 now and holds back $5,000.
- HST payable now is 13% of $45,000, which is $5,850. That goes on your March return (or the return for whatever period contains March).
- The $650 of HST on the $5,000 holdback is not payable with the March draw. It becomes payable on the earlier of the day the holdback is paid and the day it becomes payable under the contract or under the Construction Act (when the holdback period ends).
- Report the $650 in the period that earlier day falls in, even if the owner is late paying the holdback. A slow owner does not slow the tax.
Now say the job hits 90% complete on June 12, which makes it substantially complete in the CRA's eyes, and $30,000 of the price has never been billed or paid. The HST on that $30,000, $3,900, is payable on July 31 whether you've invoiced or not. Slow paperwork does not slow the tax. The holdbacks are still left out of this rule; they keep their own timing.
Draws, holdbacks and HST not lining up?
Describe your contract, your draw schedule and the holdback terms. The free assistant works out when the GST/HST on each amount is payable, which return it belongs on, and how to set up the invoices.
Check your GST/HST return before you file
The GST/HST Return Check works out every line, checks the tax you charged against the rate, sorts your input tax credits and compares the quick method. You get your due date too.
How to Show It on Your Invoices
The tax on the holdback is payable on the holdback's schedule, not the invoice date, so a clean invoice makes life easier for everyone, including the bookkeeper on the other end:
- Show the value of work for the draw ($50,000).
- Show the holdback deducted ($5,000).
- Show HST on the amount payable now ($45,000 x 13% = $5,850) and the total due ($50,850).
- On the holdback release invoice, bill the $5,000 plus the $650 of HST.
The release invoice does not set the date for the holdback tax. If the holdback became payable in an earlier period, the $650 belongs on that earlier return, invoice or no invoice. The same goes for draws: the amount becomes due on the earlier of the invoice date and the due date in your written contract, so holding the invoice back does not hold back the tax.
Every invoice also needs the information your customer must have to claim the ITC, including your GST/HST registration number. The full list is on how to charge GST/HST. If you want a second set of eyes on a draw invoice, try the construction invoice analyzer.
One trap: on certified jobs, your application for payment is not an invoice. The tax is triggered by the payment, or by the amount becoming due under the contract, not by the day you send the request to the architect.
When Your Customer Can Claim the ITC
A registered customer, such as a general contractor paying you as a sub or a business owner building a shop, can claim the ITC in the reporting period the tax becomes payable, even if they haven't paid it yet, as long as they have the paperwork. For the holdback, that means the period the holdback is paid or becomes payable, not the period of the original draw.
Most registrants have four years to claim, counted to the due date of the return for the last reporting period ending within four years after the period the ITC could first be claimed. See input tax credits for the rest of the conditions.
On your side, if you report HST on a draw or a released holdback and the customer never pays, you may be able to get that tax back; see GST/HST bad debts.
For the bigger picture on construction, read GST/HST for contractors and net tax calculation. Back to the GST/HST guide.
GST/HST Holdback and Progress Billing Questions
Do I charge HST on the holdback when I send the progress invoice?
The HST on the held-back amount is not payable until the earlier of the day the holdback is paid and the day it becomes payable. Report it then, not with the original draw, even if the owner has not paid the holdback yet.
When is HST payable on a progress billing?
On the earlier of the day the customer pays it and the day it becomes due. It becomes due on the earlier of the invoice date and the due date set in your written contract.
What is the 90% rule for construction contracts?
Under a written construction contract, GST/HST on any part of the price not yet paid or due is payable on the last day of the month after the month the work is substantially complete, which the CRA treats as 90% or more of the work done. Holdbacks are excluded.
Is my application for payment an invoice for GST/HST?
Not when the contract requires an architect, engineer or consultant to approve the work and issue a payment certificate. The request alone does not make the tax payable.
When can my customer claim the ITC on a holdback?
In the reporting period the HST on the holdback becomes payable, which is when the holdback is paid or becomes payable. Most registrants then have four years to claim it.